November 15 - November 25, 2016 Look Ahead

During this period, the development team will be clearing and grubbing organic material and brush from the site in preparation for the installation of temporary construction trailers for the construction team.  Other activity:

  • Mobilization: Installation of temporary power poles near Science and Engineering 2 will provide power to future construction trailers.

  • Sitework: Preparatory work will also begin on the development of a new access point to the construction site for heavy equipment.

  • Fencing: The construction site's fence line will also be moved from the southern edge of the South Bowl to Scholars Lane. 

  • Infrastructure: Electrical work impacting campus will take place on Friday November 25th

  • Parking: A replacement gravel parking lot will be opened adjacent to the Evolution Valley lot to enable construction adjacent to Little Lake

 

October 1- October 30, 2016 Look Ahead

  • Events: Groundbreaking Ceremony on October 14, 2016 at 1 pm in South Bowl

 

September 1 -September 30, 2016 Look Ahead

  • Fencing: Fence Installation along Little Lake and Scholars Lane 

  • Circulation: Closure of wooden bridge and unpaved path on September 23, 2016

 

August 3 - August 30, 2016 Look Ahead

  • Site Investigation: Potholing investigations throughout project site on August 3-6 and August 15-16, 2016