Construction Advisory 2

Activity

Shrub Removal
 

Duration

August 29, 2016  (7 am - 3 pm)
 

To prepare for the installation of protective fencing around the 2020 Project construction site, the Development Team will be removing a number of shrubs along the south side of Scholars Lane next to Little Lake on August 29, 2016.   The hours of activity will be between 7 am and 3 pm. Traffic flaggers will be on site to direct buses, circulation and vehicles.

No trees will be removed. 

After the shrubs are removed, between August 30 and September 2, 2016, a protective fence will be installed alongside a portion of the sidewalk on the lake side of Scholars Lane.  The amphitheater and a portion of the Bowl will remain open and accessible. 

For your safety, please be aware of barricades and detour signage.  Please email construction2020@ucmerced.edu with any comments or concerns.

Let's make it an Art Fence!

To start, a gallery of renderings of 2020 Project facilities and project details will be installed alongside the Scholars Lane portion.  If you have any interest in getting involved with adding art to the fencing in the future, please send an email to rcummings2@ucmerced.edu